ABSTRACT
This project is
purposely for determining the effects of delay and disruption on the cost of
building construction project in Nigeria, ascertaining the cost, which aim at
x-raying unnecessary delay and disruption in the normal processes of procuring
and prosecuting building and civil engineering construction work at both
pre-contract and post contract stages of construction. The factors that usually
call for these delay and disruption in construction projects of the numerous
project on the construction landscape and on the parties that are involved in
carrying out the projects. This study continued with elucidating
what the Quantity Surveyor and the other parties involved in the construction
process can do to eliminate delays and disruption in construction in
Nigeria. According to this study, inadequate planning,
incompetent project manager, variation in project scope, political factors,
price fluctuation etc., contributes to the delays and disruption of building
construction project and thereby affecting their cost also. Most of the proper
majors are recommended for the elimination of delays and disruptions on
construction project i.e Adequate pre-contract study, engaging competent
construction professionals etc.
TABLE OF CONTENTS
CHAPTER ONE
INTRODUCTION
1.1
Background of
study
1.2
Statement of
problem
1.3
Purpose of
study
1.4
Research
Questions
1.5
Significance of
study
1.6
Scope of
Study
1.7
Definition of
Terms
CHAPTER TWO
LITERATURE REVIEW
2.1
Delay and Disruption
2.2
Construction Delay and
Causes
2.2.1 Why Construction Projects are delayed and
Abandoned
2.2.2 Common problems
causing delay in construction
2.2.3 Inadequate
pre-contract study and Planning
2.2.4 Award of
Contract
2.2.5 Variations
2.2.6 Fluctuations
2.2.7 Natural
Disaster
2.2.8 Poor Executive
Capacity of the Contractor
2.3
Cause of High Costs of Construction
2.4
Time Over-Runs and
Cost
2.5
Delay and Disruption in Construction in Summary
CHAPTER THREE
METHODOLOGY
3.1
Research
Design
3.2
Area of
Study
3.3
Population of
Study
3.4
Sampling Technique
3.5
Instrument for Data Collection
3.6
Validity of an Instrument
3.7
Reliability of
Instrument
3.8
Method of Data
Collection
3.9
Method of Data
Analysis
CHAPTER FOUR
PRESENTATION AND
ANALYSIS 0F DATA OR RESULT
4.1
Results
CHAPTER FIVE
DISCUSSION AND
CONCLUSION OF RESULTS
5.1
Discussion of Findings
5.2
Conclusion of the
Study
5.3
Recommendation
5.4
Implication of the Findings
5.5
Suggestion for Further
Study
5.6
Limitation of
Study
REFERENCES
APPENDIX
LIST OF TABLES
Table
1:
Causes of Delay and Disruption are Mainly Political Situation Limited Movement
between areas award Project To Lowest bid price.
Table
2:
Cause of Delays and Disruptions in Construction Projects
Table
3:
Price Fluctuation was Identified as the most Important Factor Responsible for
the Escalation of Project Costs
Table 4:
Fluctuation Claim
Only arise where there are Increase in price but no Refund for the price
Decrease and this affect Building costs.
Table
5:
Delayed and disrupted disruption project will yield to extra cost and poor
construction management to the client and contractors.
Table
6:
Variation of Addition, omition and Substitution Affects Construction cost.
LIST OF FIGURE
Example of Abandon
Project
CHAPTER ONE
INTRODUCTION
1.1
BACKGROUND OF THE STUDY
Most town and cities in Nigeria are dotted with projects that are being
delayed, disrupted, and uncompleted. Explanations giving for
the stages of each buildings projects is varied and sometimes attributed to
lack of financial, human and material resources with which to execute the
projects. It is common in Nigeria especially now
that the country is suffering from depression in the economy. It is
often bad to see huge capital investments being disrupted and abandoned.
Any attempt to delay and disrupt a construction project, will have terrible
consequences on every aspect of the nation’s activities which will be severe
and unwelcome.
Delays and disruptive in construction has some effects on its cost and very
retrogressive in a developing economy like Nigeria and needs to be properly
addressed and tackled with all the courage and effort that we can muster.
1.2
STATEMENT OF PROBLEM
One of the biggest problems associated with most of the construction projects
in Nigeria today is problem of delays and disruptions at both the pre-contract
and post-contract stages of construction in building and civil engineering
works.
The cost of building increases at the cause of delays and disruption in
construction because of variation. many construction project in Enugu needed
huge capital outlay and time to execute them and any attempt to delaying and
disrupting the construction proper will result to terrible consequences that
will affect the economical control and building cost.
1.3 PURPOSE OF THE STUDY
The purpose of this study is as follows –
·
To investigate into most
delayed and disrupted construction projects
·
To ascertain the effects
of delays and disruptions on cost of building construction.
·
To examine the effect of
fluctuation in prices on construction projects costs.
·
To examine the costs of
delayed and disrupted construction project to clients, contractors, the
professionals that are engaged and the nation, in particular Enugu state.
·
To examine the effects
of variation in design on construction project costs.
1.4 RESEARCH
QUESTION
1. What are the causes of delays and disruptions in
construction projects?
2. What are the effects of delays and disruptions
on building construction project cost?
3. Do fluctuations in prices bring about changes in
construction project cost?
4. What the costs are of delayed and disrupted
construction projects to the clients, contractors, the professionals that are
engaged in the field?
5. In what ways can variations in design affect
construction cost?
1.5 THE
SIGNIFICANCE OF THE STUDY
This study will be beneficial to the most construction industry in Nigeria
because once a project is initiated and manage properly it will eliminate high
cost of procurement and a lot profit are involved.
Also this
will help in planning and execution of future construction project executions,
especially the quantity surveyor in the feasibility and planning stages of a
proposed scheme and preparation of work method and schedules by the building
manager.
The study also intend to bring together, the causes of construction delays and
disruptions and also tries to ascertain the costs, which will help the
construction firms, Engineers, Surveyors and construction managers to
initialize and control their project without lost or poor management.
1.7
DEFINITION OF TERMS
From the Oxford advanced learner’s English dictionary, delay implies the
process or action of being slow being late or linger and also explain
disruption as the action of making it difficult for something to proceed.
Delay – delay in construction
can be defined as an act whereby projects execution is slow or interrupted one
time or the other, thereby leading to unnecessary extension in the programme of
work from what was initially scheduled.
Disruption – disruption
in construction projects can be defined as an act or sites partially or
completely deserted at one time or the other for the reasons of certain
exigencies which have resulted in prolonged delays which are not in accordance
with the programme of work in use extension of time or postponement as
initially scheduled.
Cost – the estimated
amount of money that will be needed for something or the price that should be
charged for something.
Also, it implies the effort, loss or damage that is involved in order to do or
achieve something.
Construction – the
process or method of building or making something, especially road, building,
bridges etc.
Department | Bio-Chemistry |
Project ID Code | BCH0018 |
Chapters | 5 Chapters |
No of Pages | 68 pages |
Methodology | Descriptive |
Reference | YES |
Format | Microsoft Word |
Price | ₦4000, $15 |
|
|
Contact Us On | +2347043069458 |